To paint a room it takes mike 75 minutes, Joan 60 minutes, and Kyle 80 minutes when each person works alone. If all three work together how long will the painting take?

Respuesta :

60 minutes at max. that is all the info i was given

Mike takes 75 minutes to paint the room. So, in 1 minute the fraction of the room Mike paints is [tex] \frac{1}{75} [/tex].

Likewise, in 1 minute the fraction of the room Joan paints is [tex] \frac{1}{60} [/tex].

Lastly, in 1 minute the fraction of the room Kyle paints is [tex] \frac{1}{80} [/tex].

Now, let [tex] t [/tex] be the number of minutes taken to paint the whole room when all three are working together.

Then, in 1 minute the fraction of the room the three paint will be [tex] \frac{1}{t} [/tex].

This can be written as:

[tex] \frac{1}{t}=\frac{1}{75}+\frac{1}{60}+\frac{1}{80}=\frac{17}{400} [/tex]

Therefore, If all three work together then they will finish the room in:

[tex] t=\frac{400}{17}\approx 23.53 minutes [/tex]