For a Design-Build Schedule to be admissible evidence in court, it must contain the Design Activity Sequence, Procurement Activity Sequence and the Construction Activity sequence. Which of the following must also be on the preliminary schedule?
A. A bar-chart with owner-furnished items and planned weather losses each month
B. A time scaled with owner-furnished items and planned weather losses at the end
C. A bar-chart with planned versus as-built activities, sequence changes & all delays
D. A time scaled with owner-furnished items and planned weather losses each month