Respuesta :
Answer:
(A) Debit to Work in Process of $79,000
Explanation:
Solution:
Total Raw Material Cost $83,000
(Less) Indirect Materials cost $4,000
Total raw materials amount $79,000
debited for Work in Process
Hence the right answer of Work in Process is $79,000.
Answer:
A)debit to Work in Process of $79,000
Explanation:
The raw materials acquired from the storeroom is $83,000 out of which $4,000 is indirect material. Therefore, the remainder $79,000 must be included as Work In Process.
Option (B) the entry is correct, however, the amount mentioned is incorrect. While the Option (C) is incorrect as the question refers to the journal entry for raw materials acquired from the storeroom.
Lastly, Option (D) is incorrect as Raw Materials are credited not debited. This is due to the fact that they are classified as asset and are being used for production. Therefore, should be credited to reduce the Raw materials available.
Hence, the Option (A) is correct both in terms of journal entry and amount i.e. debit to Work in Process of $79,000