The cumulative average labor hours to assemble the first five units of product A were 15.882 hours. If the learning curve, based on the previous experience with similar products, is 85%, what is the estimated time (labor hours) that will be required to assemble the 20th unit?

Respuesta :

Answer:

Estimated time required to assemble the 20th unit= 8.836 hours

Explanation:

The learning curve theory states that as the cumulative output doubles the cumulative average time taken till date is reduced to a certain percentage of the previous time. This percentage is called learning rate; and is given as 85% in this question.

The cumulative average time is determined using the formula below:

Y= aX^b

a - time taken for the first unit produced

b = log LR/Log 2

X- cumulative units till date

Y - cumulative average time taken for X units

LR- Learning rate

So we can apply this formula to our question

b  = Log 0.85%/Log 2 = -0.23446

15.882 = a * 5^(-0.23446)

15.882 = a * 0.685671

a =15.882/0.685671

a =23.16271007

Time taken for the first unit =23.16 hours

Estimated time taken to assemble 20th units:

= Total time for 20units -Total time for 19units

= (23.16×(20^-0.23446)×20) -  (23.16×(19^-0.23446)×19)

= 229.4949 -229.4949

= 8.836 hours

Note:  total time = Cumulative average time × Cumulative number of units

Estimated time required to assemble the 20th unit= 8.836 hours