Answer:
a. Project A
Explanation:
The computation of the expected return is shown below:
For Project A
= (0.6 × $200,000 + 0.4 × $50,000)
= $120,000 + $20,000
= $140,000
For Project B
= (0.7 × $150,000 + 0.3 × $30,000)
= ($105,000 + $9,000)
= $114,000
Since in the Project A, the value doubles means = $100,000 × 2
And, if the succeeding percentage is 0.6 then its failing percentage is 0.4
So as we that the project A has an high expected return than the Project B so the Project A should be invested