A new CEO has come into your company and has promptly shut down your project because it no longer met the business needs of the company. While not pleased with the decision, you document the level and completeness of the project to date. What activity or process is this part of? a. Close Project or Phase b. Control Scope c. Validate Scope d. Close Procurements