Respuesta :
Answer:
The correct answer is option (c) $264 underapplied
Explanation:
Given data;
Direct labour hour = 22160
Total Manufacturing overhead cost= $585,024
Actual direct labor hour = 22150
Actual Manufacturing overhead cost = $585024
Calculating the Predetermine overhead rate using the formula;
Predetermined Overhead rate=Total Overhead Cost/Total Direct Labor Hour
Predetermined Overhead rate = $585024/22160
=$26.4 per labor hour
To determine the under-applied amount of overhead cost, we use the formula;
Under−Applied amount= Estimated Overhead Cost*Actual Overhead Cost
Substituting into the formula, we have
(22150*26.4)-585024
Under applied = $ 264