A company uses activity-based costing to determine the costs of its three products: a, b, and


c. the budgeted cost and cost driver activity for each of the company's three activity cost pools follow. compute the activity rates for each of the company's three activities.

Respuesta :

Answer:

$3.10 ; $2.10 and $14.20

Explanation:

The computation of the activity rates is shown below:

For Activity 1

= Budgeted cost ÷ Total budgeted activity of cost driver

= $94,550 ÷ (18,200 + 8,100 + 4,200)

= $94,550 ÷ 30,500

= $3.10

For Activity 2

= Budgeted cost ÷ Total budgeted activity of cost driver

= $53,550 ÷ (7,100 + 13,200 + 5,200)

= $53,550 ÷ 25,500

= $2.10

For Activity 3

= Budgeted cost ÷ Total budgeted activity of cost driver

= $59,995 ÷ (1,175 + 1,000 + 2,050)

= $59,995 ÷ 4,225

= $14.20