Answer:
There will be required 590 repair persons.
Step-by-step explanation:
Lets count the amount of minutes that are going to be used per week repairing. The amount of minutes of repair work required per week is
100*23 + 100*42+ 100*19 + 150*27 + 150*35 = 17700.
Each worker works 6 hours per day in average and 5 times per week. This means that each worker will do 30 hours of work each week. Therefore, we will need 17700/30 = 590 workers (In practice you should contract a few more, like 600, just in case).