Answer:
$5.4 and $5.4
Explanation:
The formula and the computation is shown below:
= Total setup cost ÷ total direct labor hours
= $91,800 ÷ 102,000 hours
= $0.9
For plus:
Setup cost is
= $0.9 × 6
= $5.4
And,
For Max:
= $0.9 × 6
= $5.4
We simply multiplied the per unit with the direct labor per unit so that the allocation to each unit could come