Respuesta :
Answer:
C) negative at a discount rate of 20%.
Explanation:
IRR is the interest rate at which the present value of the project or investment becomes zero. The discount rate above this rate will result the negative NPV and Below this rate will result the positive NPV.
10% is lower than the IRR of 15%, so the NPV should be positive.
20% is higher than the IRR of 15%, so the NPV should be negative.
15% is equal to the IRR of 15%, so the NPV should be zero.
Answer:
The Correct answer for the given condition is "C"
Explanation:
Internal rate of return is the rate at which the NPV (Net Present Value) either Positive or Negative the capital of the project will be Zero all the cash flows. Therefore, the net present Value is Zero at the interest rate of IRR equal to 15 percent.
If the value of IRR is above the given interest rate, Net Present value will be negative
And
If the value of IRR is below the given interest rate, Net Present value will be positive