Answer:
1,065 U
Explanation:
Materials Price Variance = Actual Quantity Purchased * (Standard Price – Actual Price)Actual Price= Total Cost / Quantity Purchased
= ($27,690 /21,300 )=$ 1.3
=21,300* [$1.25 – $1.3]
=21,300*0.05
=1,065 U
During May, the materials price variance for part XBEZ52 was 1,065 which is Unfavourable because the actual