Answer:
The labor rate variance for the month = $1890
Explanation:
Given values:
Standard labor hour per unit = 3.3 hours
Standard labor rate = $16.15 per hour
Actual hours worked = 6,300
Actual total labor cost = $103,635
Actual output = 2,000 units
Now, we calculate the labor rate variance with the help of given information. Below is the calculation of Labor rate variance.
Labor rate variance = ( Actual labor cost) – (Standard rate × Actual hours)
= 103635 – (16.15 × 6,300)
= $1890