Answer:
D.) $75,000
Explanation:
Amount of revenue recognized = Cost incurred to date / Estimated total cost * Contract price
Cost incurred to date=60,000
Estimated total cost=400,000
Contract price=500,000
Amount of revenue recognized= 60,000/400,000 * 500,000
=0-15 * 500,000
=$75,000
Amount of revenue recognized in year 1 is $75,000