Answer:
a. Determine the predetermined overhead rate.
the predetermined overhead rate = total budgeted overheard costs / total budgeted direct materials used = $840,000 / $400,000 = 2.1 = 210%
b. Write the overhead costs incurred and the amounts applied to jobs during the year using the predetermined overhead rate and determine whether overhead is overapplied or underapplied.
applied overhead costs = actual direct materials x overhead rate = $528,000 x 210% = $1,108,800
over applied overhead = actual overhead - standard overhead = $1,041,000 - $1,108,800 = -$67,800 favorable variance
c. Prepare the adjusting entry to allocate any over- or underapplied overhead to Cost of Goods Sold.
Dr Manufacturing overhead 67,800
Cr Cost of goods sold 67,800
Explanation:
budget:
overhead costs, $840,000
direct materials costs, $400,000
actual:
overhead costs, $1,041,000
direct materials costs, $528,000