Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go-karts: Deluxe and Basic. Activity Expected Costs Expected Activity Handling materials $ 625,000 100,000 parts Inspecting product 900,000 1,500 batches Processing purchase orders 105,000 700 orders Paying suppliers 175,000 500 invoices Insuring the factory 300,000 40,000 square feet Designing packaging 75,000 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on 125,000 budgeted direct labor hours. 2. In January of this year, the Deluxe model required 2,500 direct labor hours and the basic model required 6,000 di

Respuesta :

Answer:

Results are below.

Explanation:

First, we need to calculate the plantwide predetermine manufacturing overhead rate:

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

total estimated overhead costs for the period= (625,000 + 900,000 + 105,000 + 175,000 + 300,000 + 75,000)

total estimated overhead costs for the period= $2,180,000

Predetermined manufacturing overhead rate= 2,180,000 / 125,000

Predetermined manufacturing overhead rate= $17.44 per direct labor hour

Now, we can allocate overhead to each product line:

Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base

Deluxe:

Allocated MOH= 17.44*2,500

Allocated MOH= $43,600

Basic:

Allocated MOH= 17.44*6,000

Allocated MOH= $104,640