Answer: The actual cost of materials was less than the standard cost
Explanation:
Net materials cost variance = Favorable materials price variance + Favorable materials quantity variance
= 380 + (-120 unfavorable)
= 380 - 120
= $260 favorable
As the materials cost variance is favorable, it means that the actual cost of materials was less than what was budgeted for it or rather its standard cost.