As the sprint planning progresses, the developers realize that the workload may be greater than their capacity to complete the work. which two are valid actions?

Respuesta :

As the sprint planning progresses, the developers realize that the workload may be greater than their capacity to complete the work. two are valid actions:

  • Remove or change selected Product Backlog Items
  • The Development Team ensures that the Product Owner is aware, starts the Sprint and monitors progress

They can do two things to ensure the reputation of the team by making the owner of the product know about their lacking and start measuring their routine developments. They can also remove the hindrances of product making.

Learn more about sprint planning:

https://brainly.com/question/20114192