Answer:
(b)
Total available time = 18x60 =1080 min.
Total processing time = 320x0.5 = 160 min
Total set up time = 320x1 -320 min.
Total rework time = ( 1+0.5) =120 min.
Total Non value added time = set up time + rework time 320+120 = 440 min.
(c) Total value added time = processing time = 160 min.
(d) Total waste time = set up time + rework time + Idle time 320+120+ 480 = 920 mn.
(e) OEE = processing time / time available = 160/1080 = 0.1481 = 14.81%